Article 45 The requisition of the following land shall be approved by the State Council:

1. Basic farmland;
2. Land exceeding 35 hectares outside the basic farmland;
3. Other land exceeding 70 hectares.

Requisition of land other than prescribed in the preceding paragraph shall be approved by the people's governments of provinces, autonomous regions and municipalities and submitted to the State Council for the record.

Requisition of agricultural land should first of all go through the examination and approval procedure for converting agricultural land into land for construction purposes according to the provisions of Article 44 of this law. Whereas conversion of land is approved by the State Council, the land requisition examination and approval procedures should be completed concurrently with the procedures for converting agricultural land to construction uses and no separate procedures are required. Whereas the conversion of land is approved by people's governments of provinces, autonomous regions and municipalities within their terms of reference, land requisition examination and approval procedures should be completed at the same time and no separate procedures are required. Whereas the terms of reference has been exceeded, separate land requisition examination and approval procedures should be completed according to the provisions of the first paragraph of this article.

Article 46 For requisition of land by the State the local people's governments at and above the county level shall make an announcement and organize the implementation after the approval according to the legal procedures.

Owners or users of the land requisitioned should, within the time limit specified in the announcement, go through the compensation registration for requisitioned land with the land administrative departments of the local people's governments on the strength of the land certificate.

Article 47 In requisitioning land, compensation should be made according to the original purposes of the land requisitioned.

Compensation fees for land requisitioned include land compensation fees, resettlement fees and compensation for attachments to or green crops on the land. The land compensation fees shall be 6-10 times the average output value of the three years preceding the requisition of the cultivated land. The resettlement fee shall be calculated according to the number of agricultural population to be resettled. The number of agricultural population to be resettled shall be calculated by dividing the amount of cultivated land requisitioned by the per capital land occupied of the unit whose land is requisitioned. The resettlement fees for each agricultural person to be resettled shall be 4-6 times the average annual output value of the three years preceding the requisition of the cultivated land. But the maximum resettlement fee per hectare of land requisitioned shall not exceed 15 times of the average annual output value of the three years prior to the requisition.

The standards for land compensation and resettlement fees for land requisitioned shall be determined by various provinces, autonomous regions and municipalities in reference to the land compensation fees and resettlement fees for cultivated land requisitioned.

The standards for compensating for ground attachments and green crops on the land requisitioned shall be determined by various provinces, autonomous regions and municipalities.

In requisitioning vegetable fields in suburban areas, the units using the land should pay new vegetable field development and construction fund.

Whereas the land compensation fees and resettlement fees paid according to the provisions of the second paragraph of this article are not enough to maintain the original level of living, the resettlement fees may be increased with the approval of the people's governments of provinces, autonomous regions and municipalities. But the combined total of land compensation fees and resettlement fees shall not exceed 30 times the average output value of the three years prior to the requisition.

In special circumstances, the State Council may raise the standards for land compensation and resettlement fees for land requisitioned according to the social and economic development level.

Article 48 After the plan for land compensation and resettlement fees is finalized, related local people's governments shall make an announcement and hear the opinions of the rural collective economic organizations and peasants whose land has been requisitioned.

Article 49 Rural collective economic organizations shall make public to its members the receipts and expenditures of the land compensation fees for land requisitioned and accept their supervision.

It is forbidden to embezzle or divert the land compensation fees and other related expenses.

Article 50 Local people's governments at all levels shall support rural collective economic organizations and peasants in their efforts toward development and operations or in starting up enterprises.

Article 51 The standards for land compensation and method of resettlement for land requisitioned for building large and medium-sized water conservancy projects and hydroelectric power projects shall be determined separately by the State Council.

Article 52 In the process of the feasibility study for construction projects, land administrative departments may examine the related matters concerning the land for construction purposes and put forward their proposals according to the general plans for the utilization of land, the annual plan for the use of land and standards for land used for construction purposes.

Article 53 Whereas a construction project approved needs land owned by the State for construction purposes, the construction unit should file an application with land administrative department of the people's government at and above the county level with the power of approval on the strength of related documents required by law and administrative decrees. The land administrative department shall examine the application and submit it to the people's government at the same level for approval.

Article 54 A paid leasing should be go through in use of land owned by the State by a construction unit. But the following land may be obtained through government allocation with the approval of the people's governments at and above the county level according to law:

1. Land for use by government organs and for military use;
2. Land for building urban infrastructure and for public welfare undertakings;
3. Land for building energy, communications and water conservancy and other infrastructure projects supported by the State.
4. Other land as provided for by the law and administrative decrees.

Article 55 Construction units that have obtained State-owned land by paid leasing can use the land only after paying the land use right leasing fees and other fees and expenses according to the standards and ways prescribed by the State Council.

Starting from the date when this law comes into effect, 30% of the land compensation fees for new construction land shall be handed over to the central finance, with the rest 70% to be retained by related local people's governments, for the development of land for cultivation.

Article 56 In using State-owned land, construction units should use the land according to the provisions of the contract for compensated use of leased land use right or according to the provisions of the documents of approval concerning the allocation of land use right. The change of the land to construction purposes should get the consent from the land administrative departments of the related people's governments and be submitted to the people's governments that originally give the approval for the use of land. In changing the purpose of land within the urban planned areas, the consent should be obtained form the related urban planning administrative departments before submission for approval.

Article 57 In the case of temporary using State-owned land or land owned by peasant collectives by construction projects or geological survey teams, approval should be obtained from the land administrative departments of local people's governments at and above the county level. Whereas the land to be temporarily used is within the urban planned areas, the consent of the urban planning departments should be obtained before being submitted for approval. Land users should sign contracts for temporary use of land with related land administrative departments or rural collective organizations or villagers committees depending on the ownership of the land and pay land compensation fees for the temporary use of the land according to the standard specified in the contracts.

Users who use the land temporarily should use the land according to the purposes agreed upon in the contract for the temporary use of land and should not build permanent structures.

The term for the temporary use of land shall not usually exceed two years.

Article 58 In one of the following cases, the land administrative departments of related people's governments shall recover the land use right of State-owned land with the approval of the people's governments that originally gives the approval or the people's governments with the power of approval:

1. Use land for the sake of public interests;
2. Use land for adjustment in re-building old city districts in order to implement urban construction plans;
3. When the term for the land use right expires according to what is agreed upon in the contract for compensated use of land, the land user has failed to apply for extension or failed to get approval for extension;
4. The use of land originally allocated has been stopped due to cancellation or removal of units;
5. Roads, railways, airports and mining sites that have been approved to be abandoned.

Proper compensation should be given to land use right users whereas the use right of State-owned land is recovered according to the provisions of 1 and 2 of the preceding paragraph.

Article 59 Construction of township enterprises, public facilities and public welfare undertakings of townships (towns) and rural villagers' houses should be rationally laid out according to the village or market town plans according to a comprehensive development plan, with good supporting facilities. Land used for construction purposes shall conform to the general plans for the utilization of land of townships (towns) and their annual plan for the use of land and the examination and approval procedures should be completed according to the provisions of Article 44, Article 60, Article 61 and Article 62 of this law.

Article 60 In using the land for construction purposes defined in the general plan for the utilization of land of townships (towns) to start up enterprises or joint ventures together with other units or individuals by way of using land use right as shares, the rural collective economic organization shall file an application with land administrative departments of the local people's governments at and above the county level on the strength of documents of approval. The applications shall be approved by the local people's governments at and above the country according to the terms of reference provided for by various provinces, autonomous regions and municipalities whereas the use of land involving the occupation of agricultural land, the examination and approval procedures provided for in Article 44 of this law shall be followed.

Land for construction purposes in starting enterprises provided for in the preceding paragraph shall be put under strict control. Provinces, autonomous regions and municipalities shall determine the standards for land use according to different trades and scale of operation of township enterprises.

Article 61 In using land for building public facilities and public welfare facilities, townships (towns) shall file an application with land administrative departments of local people's governments at and above the county level after being examined by the township (town) people's governments at and the application shall be approved by the local people's governments at and above the county level according to the term of reference provided for by provinces, autonomous regions and municipalities. Where occupation of agricultural land is involved, the examination and approval procedures provided for in Article 44 of this law are required.

Article 62 One rural household can own one piece of land for building house, with the area not exceeding the standards provided for by provinces, autonomous regions and municipalities.

Construction of rural houses should conform to the general plans for the utilization of land of townships (towns) and the original land occupied by houses and open spaces of villages should be used as much as possible for building houses.

The use of land for building houses should be examined by the township (town) people's governments and approved by the county people's governments. Whereas occupation of agricultural land is involved the examination and approval procedure provided for in Article 44 of this law is required.

The application for housing land after selling or leasing houses shall not be approved.

Article 63 The land use right of peasant collectives shall not be leased, transferred or rented for non-agricultural construction, except in the case of legal transfer of the land that conforms to the general plan for the utilization of land and legally obtained by enterprises due to bankruptcy or acquisition.

Article 64 Buildings or structures put up before the general plan for the utilization of land and unconformable to the general plans are not allowed to be rebuilt or expanded.

Article 65 In one of the following cases, the rural collective economic organizations may recover the land use right with the approval of the people's government that gives the approval for the use of land:

1. Land needed for building public facilities and public welfare undertakings of townships (towns) and villages;
2. Land not used according to the purposes approved;
3. Land not used any more due to cancellation or removal of the original units.

Proper compensation shall be given to land users in the case of recovering the land owned by peasant collectives provided for in item 1 of the preceding paragraph.

CHAPTER SIX SUPERVISION AND EXAMINATION

Article 66 Land administrative departments of the people's governments at and above the county level shall exercise supervision and examination on violations to the land administrative law and administrative decrees.

Supervising personnel in such a regard should be well acknowledged with the land administrative law and decrees, loyal to their duties and justice in enforcement of the law.

Article 67 In performing their supervising and examination duties, the land administrative departments of the people's governments at and above the county level have the right to adopt the following measures:

1. Demand for documents and materials concerning land-use rights from units or individuals for examination, review or copying.

2. Demand explanations from units or individuals concerned in regard to land-use rights;

3. Enter into land illegally occupied by units or individuals under examination to carry out on-the-spot surveys, and

4. Command units or individuals that have occupied land illegally to stop their acts of violating the land administrative law and decrees.

Article 68 In performing their duties, whereas there is the need to carry out on-the-spot survey or demand units or individuals concerned to present documents and materials or explanations, supervising personnel should present certificates of land supervision and examination.

Article 69 Units or individuals concerned should provide active support and cooperation to land administrative departments of the people's governments at and above the county level in their supervision and examination of violations to land administration and provide all the conveniences to facilitate but not in any way refuse or obstruct their work in such a regard.

Article 70 Whereas land administrative departments of the people's governments at and above the county level have found government functionaries to have committed violations during their supervision and examination, they shall give them administrative punishments whereas the punishments are due. Whereas they do not have the right to handle the cases, they should put forward proposals for administrative punishments to the administrative supervision organs at the same level or at a higher level. The related administrative supervision departments shall mete out punishments according to law.

Article 71 Whereas the land administrative developments of the people's governments at and above the county level have found violations to have constitute a crime in their supervision and examination, they shall hand over the case to related government organs to affix criminal responsibilities. Whereas the case cannot constitute a crime, administrative punishments shall be meted out.

Article 72 Whereas related land administrative departments have failed to give administrative punishments due, the land administrative departments of the people's governments at a higher level have the right to command the land administrative departments to take punishment decisions or give administrative punishments directly and give administrative punishments to the person responsible of the related land administrative departments.

CHAPTER SEVEN LEGAL RESPONSIBILITIES

Article 73 For illegal transfer of land through trade or other forms, land administrative departments of the people's governments at and above the county level shall confiscate the proceeds from the transfer. For converting agricultural land into land for construction uses in violations to the provisions of the general plans for the utilization of land, an order shall be given to dismantle the new buildings or other facilities illegally built on the land illegally transferred for restoration of the land to the original state, and whereas in such cases no violation to the general plan for the utilization of land, the new building and other facilities on the land illegally transferred shall be confiscated and a fine may be imposed. Administrative punishments shall be given to persons in charge and persons directly responsible and whereas the case constitutes a crime, criminal responsibilities shall be affixed.

Article 74 Occupying cultivated land to build kilns or graves or build houses, dig sand, collect stones, do mining or collect soil from the cultivated land without authorization, thus damaging the conditions for growing crops or causing desertification and salinization due to land development in violation of this law, the land administrative departments of the people's governments at and above the county level shall order correction or improvetment within a prescribed time limit and concurrently impose a fine. Whereas the case constitute a crime, criminal responsibility shall be affixed.

Article 75 Refusing to perform land reclamation obligations in violation of this law, the land administrative departments of the people's governments at and above the county level shall order correction within a prescribed time limit. Whereas no correction is made within the time limit, a payment of land reclamation fees specially used for land reclamation by the violator shall be ordered and a fine may be imposed concurrently.

Article 76 Occupying land without approval or by deception, the land administrative departments of the people's governments at and above the county level shall order to return the land illegally occupied; turning to agricultural land into land for construction uses without authorization in violation of the general plans for the utilization of land, dismantling of the new buildings and other stuctures on the land illegally occupied within a prescribed time limit shall be ordered and whereas the act has not violated the general plans for the utilization of land, the new buildings and structure concerned shall be confiscated and a fine may be imposed concurrently. Persons in charge of the unit that occupies land illegally and the people directly responsible shall be given administrative punishments and whereas the case constitutes a crime, criminal responsibility shall be affixed. For an occupation of land in excess of the approved amount, part in excess shall be regarded as land illegally occupied.

Article 77 Occupying land by rural villagers for building houses without approval or by deception shall be ordered a return of the land illegally occupied and dismantle the new houses built on the land illegally occupied by land administrative departments of the people's governments at and above the county level.

For occupation of land in excess of the standards prescribed by the provinces, autonomous regions and municipalities, the land in excess of the standards shall be regarded as having been illegally occupied.

Article 78 Approving the occupation of land without the power of approval, beyond the term of reference, or not according to the purposes defined in the general plans for the utilization of land or approving the occupation or requisitioning of land in violation of the legal procedures, the documents of approval shall be invalid and the persons in charge and personnel directly responsible for illegal requisition or use of land shall be given administrative punishments. Whereas the case constitutes a crime, criminal responsibilities shall be affixed. The land illegally approved and used shall be recovered. Whereas parties concerned refuse to return, the case shall be regarded as illegal occupation of land.

Whereas illegal requisition and use of land have caused damages to parties concerned, the party responsible shall bear the responsibilities of compensation according to law.

Article 79 Embezzling or diverting the use of land compensation fees and other related expenses of the units whose land is requisitioned, criminal responsibilities shall be affixed whereas the case constitutes the crime and administrative punishments shall be meted out whereas the case is not serious enough to constitute a crime.

Article 80 A refusal to return of land use right upon a legal recovering of the land or an expiration of temporary land use term or State-owned land is used not according to the purposes approved, the land administrative departments of the people's governments at and above the county level shall order the return of the land and impose a fine.

Article 81 Leasing, transferring or renting the use right of land owned by peasant collectives for non-agricultural construction uses, the land administrative departments of the people's governments at and above the county level shall order correction within a prescribed time limit, confiscate the proceeds concerned and impose a fine.

Article 82 Refusing to go through the land alteration registration according to the provisions of this law, the land administrative departments of the people's governments at and above the county level shall order the parties concerned to go through the procedure within a prescribed time limit.

Article 83 Whereas orders have been issued to dismantle the new buildings and other facilities on the land illegally occupied within a prescribed time limit according to the provisions of this law, the construction unit or individual shall stop operation immediately and dismantle them by themselves. Whereas the operation continues, the organ which decided for the punishment decisions has the right to stop it. Whereas a construction unit or individual refuse to accept the administrative punishment decisions on dismantling the buildings and other facilities, it may bring the case before the people's court within 15 days starting from the day when the decision is received. Whereas a unit or individual fails to put the case in proceeding when the time limit expires and yet refuses to do the dismantling, the organ making the punishment decision shall apply for compulsory exercise with the people's court and the cost arising therefrom shall be borne by the law violator.

Article 84 Dereliction of duty, abuse of power for personal gains and practise favouritism by personnel of the land administrative departments shall be affixed of criminal punishments according to criminal law whereas the case is serious enough to constitute a crime or imposed of administrative punishments whereas the case is not serious enough to constitute a crime.

CHAPTER EIGHT SUPPLEMENTARY PROVISIONS

Article 85 This law applies to the use of land by Sino-foreign joint equity and cooperative ventures, and wholly foreign-owned enterprises. Whereas there are separate provisions by law, those provisions shall prevail.

Article 86 The law shall come into force starting from January 1, 1999.

Appendix: Related articles in the Criminal Law:

Article 228 Illegal transfer or trade of land use right for personal gains in violation of the land administrative law and regulations shall be sentenced to a prison term of less than three years or to forced labor, with a concurrent fine amounting to more than 5% and less than 20% of the proceeds from the illegal transfer or trading whereas the case is serious enough, and whereas the case is very serious, it shall be sentenced to a prison term ranging from more than three years to less than seven years, with a fine ranging from more than 5% to less than 20% of the proceeds from the illegal transfer or trading of the land use right.

Article 342 Illegal turning of cultivated land occupied into other uses in a big amount to cause damages to large tracts of cultivated land in violation of the land administrative law and regulations, a punishment of from less than five years' in prison or forced labor shall be given, together with a fine concurrently or separately.

Article 410 Whereas government functionaries are found to have committed deception or forgery for personal gains in violation of the land administrative law and regulations or have abused their power to illegally approve the requisition of land or under-sell the use right of State-owned land and the cases are serious, a punishment of less than three years in prison or forced labor shall be given; whereas the cases have caused very big losses to the State or collectives, a prison term ranging from more than three years to less than seven years shall be meted out.

China Easy Booking

  • Apply for a visa to China

    Get your China visa today, from China visa service center you trust-at0086 China Service Mall. We serve residents of all countries who want to get the China visa application Easy, fast, affordable, reliable.

    Book now
  • Book a China hotel

    Want to find a hotel in china including Beijing hotel, Shanghai hotel and Guangzhou hotel? We offer china hotel reservations. Just click and choose what your needed, we will exert our energy to help you find a hotel in china. Make your China hotel reservation online booking now!

    Book now
  • Find a Chinese translator

    Need Translation service in China including in Shanghai and in Beijing? At0086 China Service Mall provides some practical information about translation service in China. Just click and choose what your needed, we will exert our energy to help you find good translators and interpreters. Easy, fast, affordable, reliable.

    Book now
  • Rent a car in China

    Want to rent a car in China ? You can find car rental service in Beijing and in Shanghai from China Service Mall-the worldwide greatest reservation center for china service and rent a car in China in cheap price. Reserve your car rental service from at0086.

    Book now
  • Plan a trip to China

    China tours guide provide you china travel including Beijing tour, Shanghai tour, Xian tour, Yunnan tour and Tibet travel information. You can book china tour package from China Service Mall. Click here for china tours guide information.

    Book now
  • Rent an office in China

    Want to find an office for rent in china including in Beijing or in Shanghai? We offer office lease reservations. Just click and choose what your needed, we will exert our energy to help you find office for lease in china. Make your office lease reservation online booking now!

    Book now
  • Invest in China

    Ask for China investment? You can refer to China investment information or service reservation of investment in china provided by At0086 China Service Mall.

    Book now
more reservations